Restore Previous Revision

 

 

 

 

This command allows you to "come back" to a preceding minor revision from the project tree document and redefine this revision as the latest revision. For example, a modification on a part was placed in the vault, but the modification is not required.

Reminder: Each check in creates a new minor revision of the document (and a new file).

 

Creation Stages / Use:

 

Select Restore Previous Revision... from the popup menu on the document.

 

  1. Created texts can be used in multiple documents. Click the revision to display the preview.

  2. Validate.

  3. The summary window indicates whether or not the operation is possible.

  4. Validate.

 

 

2 minor revisions are necessary in order to restore the previous revision.

 

 

Modifications / Additional information:

 

You can directly select the desired minor revision (by clicking the "+" in front of the document, then Revision, selecting the desired major revision, then the minor revision), and using the Restore as Latest Revision function from the popup menu.