This command allows to check-in the Work 
 document and all documents produced by processes.
 
Creation stages / Use:
 
Select the Work > Achievment... 
 command from the drop-down menu.
 
	- Validate the check-in box. 
 
 
 
	
	
	
		| 
 | 
			It is possible to achieve 
			 a work document only if it is linked to the Work 
			 Manager.It is possible to achieve 
			 a work document only if its processes have been executed.It is possible to cancel 
			 an achievment thanks to the contextual menu from the Work Manager in the Work 
			 status column. | 
 
 
	
	
	
		| 
 | 
			It is not possible to cancel 
			 a process execution if the work document has been achieved. 
			 The achievment must be canceled first. | 
 
 
Modifications / Additional information: 
 
This command changes the work status and its tasks to Achieved.